Does changing the start day work?
Action:
1) Select the 'Tools' menu and select 'Options'.
2) Select the 'General' tab.
3) Click on the down arrow in the 'Week start at' box and select 'Saturday'.
NOTE: The day selected must be a weekend day for the task to have the correct end date.
4) Click 'OK'.
Question:
Does changing the start day work?
Responses:
Yes, changing the start day works
No, changing the start day does not work